Implementing the outcome of a review of a participation failure decision 001-10130020



Penalty Sequence outside of 13 weeks

This table gives examples of when 3 mutual obligation failures have been applied and one of the failures in the sequence is revoked.

Item

Example

1

First mutual obligation failure in the sequence revoked

Anne has had 3 mutual obligation failures applied.

The current penalty sequence is:

  • First failure – 50%
  • Second failure – 100%
  • Third failure – cancellation

A decision to revoke the first mutual obligation failure is made by the Administrative Review Tribunal (ART). The review of decision outcome is outside of 13 weeks. Manually update the penalty sequence:

  • First failure – revoked
  • Second failure – update to the first failure 50%
  • Third failure – update to the second failure 100%

2

Second mutual obligation failure in the sequence revoked

David has had 3 mutual obligation failures applied.

The current penalty sequence is:

  • First failure – 50%
  • Second failure – 100%
  • Third failure – cancellation

A decision to revoke the second mutual obligation failure is made by the Administrative Review Tribunal (ART). The review of decision outcome is outside of 13 weeks. Manually update the penalty sequence:

  • First failure – remains unchanged 50%
  • Second failure – revoked
  • Third failure – update to the second failure 100%

3

Third mutual obligation failure in the sequence revoked

Rebecca has had 3 mutual obligation failures applied.

The current penalty sequence is:

  • First failure – 50%
  • Second failure – 100%
  • Third failure – cancellation

A decision to revoke the third mutual obligation failure is made by the Administrative Review Tribunal (ART). The review of decision outcome is outside of 13 weeks. Manually update the penalty sequence:

  • First failure – remains unchanged 50%
  • Second failure – remains unchanged 100%
  • Third failure – revoked