Child Support Strategic Performance Measure 3 (SPM3) quality checking 111-25091506
This document outlines how to conduct quality checks on applications for child support assessments, as required under Strategic Performance Measure 3.
On this page:
Aim for Accuracy and quality assurance
Sampling and allocation
Table 1: this table is for the Quality and Technical Support Delivery Support team only.
|
Step |
Action |
|
1 |
Determine if a weekly allocation needs to occur + Read more ... Each week, the Data and Analytics Division selects 50 completed applications as a sample of all decisions on applications for an administrative assessment finalised in the previous week. This sample is saved to a secured shared folder. See mySupport article How to request access to secure shared folder in ISP for information on how to request access to the Data Analytics > Business Intelligence Performance > BIP-CSP00297_SPM3_CSP folder. To meet the minimum checking requirement of 400 checks per quarter and have a consistent number of checks completed each month, allocate 3 weeks’ of samples per month to the checking panel. Have 3 weeks of decisions made in the current month been allocated?
|
|
2 |
Determine if allocation is appropriate + Read more ... Allocation must only occur for weeks where all days fall within the current calendar month. This prevents a decision finalised in one month being checked and reported against a later month. Is the date range covered by the sampling spreadsheet for the previous week entirely within the current calendar month?
|
|
3 |
Create the allocation spreadsheet + Read more ...
|
|
4 |
Specific allocations + Read more ... International applications and withdrawn decisions are allocated to specific panel members who have the specialist knowledge required to assess the correctness of the decisions relating to the SPM3 measure. If a sample shows:
|
|
5 |
General allocation + Read more ...
|
|
6 |
Notify the checking panel of allocation + Read more ... All panel members are added to the SPM3 Quality Checks MS Teams group managed by the Quality and Technical Support Service Delivery Support team. Following the creation of the allocation spreadsheet, use the SPM3 Quality Checks MS Teams chat to advise the checking panel the allocation is available. Flag the post as important. |
Verint evaluation
Table 2: this table is for quality checkers to record SPM3 evaluations into Verint.
|
Step |
Action |
|
1 |
Request access to Verint + Read more ...
Note: the type of access required field will automatically update. |
|
2 |
Select Service Officer and evaluation form + Read more ... Identify the staff member from the relevant SPM3 allocation spreadsheet in the Program Support Managers Quality shared folder. In Verint:
|
|
3 |
Evaluate application for assessment + Read more ... Review the documentation of customer contact and processing in Cuba and Pluto relating to the decision recorded on the SPM3 allocation spreadsheet. Evaluate against all relevant Operational Blueprint processes and/or child support legislation. Answer all questions in the evaluation form. See Table 2 on the Resources page for details about the criteria of each question. Questions 1 to 4 review process steps and gather information necessary to assess question 5. Question 5. Answering:
Select Submit to have the evaluation recorded for reporting. If a check is submitted in error, notify the Quality team. Note: evaluations for each month must be submitted by the last calendar day of the month. Have errors requiring remedial action been identified under questions 1-5?
|
|
4 |
Initiate remedial action + Read more ... If an error requiring further customer contact, investigation, or consideration for correction is identified, the quality checker must raise a CSO Potential Error Cuba intray with the following notepad:
Is the customer’s record locked to a Service Officer?
The Quality and Technical Support Service Delivery Support team will allocate the intrays to New Customer Team Leaders for review and action. Procedure ends here. |
Aim for Accuracy and quality assurance
Table 3: this table is for the Quality and Technical Support Delivery Support team only.
|
Step |
Description |
|
1 |
Allocation reconciliation + Read more ... The Quality and Technical Support Service Delivery Support Team receives a Verint report detailing the checks completed in the previous week. Compare the report to the allocation spreadsheets to ensure all checks that checkers have recorded as completed have been recorded in Verint. If there any discrepancies between the number of checks recorded as completed, and the number of checks captured in Verint, investigate further and ensure any missing evaluations are recorded into Verint. |
|
2 |
Error review + Read more ... Each month a Verint report detailing the checks completed in the previous month is received by the Quality and Technical Support Service Delivery Support team. Review any evaluation where an error under SPM3 has been identified to ensure the recording of the error was accurate, and that appropriate remedial action has been taken. Was the SPM3 error recorded accurately?
|
|
3 |
Remedial action review + Read more ... Review the customer record to check if remedial action has been taken. Has remedial action has been completed or is in progress?
|