Carer Payment (CP) cancellations, suspensions and restorations 009-04150000



This document outlines information relating to cancellations, suspension and restorations of Carer Payment (CP) and the corresponding workflows.

Carer cancellation and suspension workflow for CP

Cancellation or suspension of Carer Payment (CP) or Carer Allowance (CA) can only be done under the following reasons of the Social Security Administration Act 1999 (SSAA).

  • s80 SSAA - loss of qualification
  • s81 SSAA - failure to comply with certain notices, or
  • s82 SSAA - failure to take action to obtain a foreign payment

Eligibility for CP

The choice to cancel or suspend CP is determined by whether the loss of payment will be temporary or not. Any determination to cancel or suspend must be documented with the reason and the section of the act quoted.

Cancellation of CP

Carer Payment (CP) can be automatically or manually cancelled when it has been identified a carer is no longer entitled as a result of changes in either their circumstances, or the care receiver's circumstances, or if they have failed to comply with the requirements for payment. Before automatically or manually cancelling CP, care should be taken to establish that the carer is no longer eligible for payment.

See Cancellation and suspension of Carer Payment (CP) and/or Carer Allowance (CA).

Suspension of CP

CP and/or CA can be suspended and/or cancelled when a customer is no longer entitled to the payment as a result of changes in their or their care receiver's circumstances, or if they have failed to comply with the requirements for payment.

Generally, appropriate requests for information or action are issued to customers prior to any suspension action being considered and the customer has been given reasonable time to respond to the request.

CP cannot be suspended pending investigation. Before a payment is suspended or cancelled, the decision maker must be satisfied that there is sufficient evidence that the carer is either not qualified for the payment or the payment is not payable.

If the decision to suspend CP is made by Centrelink, prompt action should be taken to issue a notice of decision to the carer. This advice must clearly outline the reason their payment was suspended, including the date of effect and the payment type together with the relevant section(s) of the legislation. The advice must also include their review and appeal rights. If it is necessary to suspend CP, and the carer is also receiving CA it may also be necessary to suspend CA.

Notices of Decision must include:

  • details as to the information or action required
  • a timeframe for response (noting that this must be reasonable)
  • consequences of non-compliance
  • the relevant legislative reference under which the request has been made, and
  • the customers/carers review and appeal rights

A manual review should also be coded for the Service Officer to follow-up the suspension of CP at a later date. See Suspension of payments (CLK).

Restoration of CP

When restoring Carer Payment (CP) after cancellation or suspension, the carer’s eligibility must be re-established and payment commenced from the date the carer became eligible again. Changes of circumstances since suspension or cancellation must be updated on the system before restoration to ensure correct entitlements are paid.

Cancellation of Carer Payment CP (XWP)

CP (XWP) can be suspended, cancelled or restored automatically and manually, depending on the reason.

CP (XWP) will automatically be cancelled if:

  • the carer’s only or last payment level CA is suspended or cancelled for any reason, or
  • changed to CA HCC only or nil rate due to Education, Training and Treatment (ETT)

CP (XWP) will be automatically restored if payment level CA is restored or reinstated without a gap within 13 weeks. A Manual Follow Up (MFU) is produced if reinstated without a gap after 13 weeks.

Certain cancellation codes cannot be used for CP (XWP) because it is not subject to care receiver assessments or to care requirements (for example, constant care and the 25 hour rule). Carer level assessments such as the pension income and asset tests, portability rules and other carer playability rules still apply as normal. For more information, see Transfer from Wife Pension (WP) to Carer Payment (CP).

Carer restoration workflow for CP

When restoring Carer Payment (CP), it is important to re-establish the carer's eligibility to recommence payment, from the date the carer became eligible again. If there has been a change in circumstances, update relevant information on the system before restoring payments to avoid incorrect arrears being paid.

The Carer Restoration workflow cannot be used for third party processing where the care receiver is not a dependent child or partner of the carer. Within the workflow there will be detailed help and direct links to Operational Blue Print.

Cancellation, suspension and rejection codes for CP

The Centrelink system uses codes when a decision to cancel or suspend a payment, or to reject a claim, is recorded. A description of the code is used when communicating with customers. Carer Payment (CP) may be cancelled, rejected or suspended due to the customer not meeting specific eligibility requirements or for various other reasons. The customer will receive a letter explaining the reason for non-payment.

Contents

Cancellation and suspension of Carer Payment (CP) and Carer Allowance (CA)

Carer Restoration workflow for Carer Payment (CP) and/or Carer Allowance (CA)

Cancellation and suspension of Carer Payment (CP) and/or Carer Allowance (CA)

Restoration of Carer Payment (CP)

Cancellation, suspension and rejection codes for Carer Payment (CP)

Suspension of payments (CLK)