Assessing claim for Pensioner Education Supplement (PES) 010-05040020
For Pensioner Education Supplement (PES) Smart Centre Processing staff only.
This document outlines how to assess Pensioner Education Supplement (PES) claims.
On this page:
Determining and assessing a claim for PES entitlement
Assessing and coding PES claims
Determining and assessing a claim for PES entitlement
Table 1
Step |
Action |
1 |
PES claim completion + Read more ... A claim work item is created for allocation and processing in Process Direct where a customer submits:
Paper claims for PES will create an automatic Social Online Application (SOA) shell in Process Direct. These are processed the same as an online claim. When a SOA shell is automatically created for a paper claim no details will display. If a paper claim (SY004/SY075) has been lodged but no SOA shell is auto created, create a manual SOA shell by using the SOA Shell application in Process Direct. On the Claim Application page, a new Claim ID will display and the claim is ready for processing. If the customers previous claim is rejected (REJ) and a decision is made to reassess their entitlement, re-index the claim. |
2 |
Check if the student is receiving other payments + Read more ... If the customer is receiving:
|
3 |
JobSeeker Payment (JSP) or Youth Allowance (YA) (job seeker) customers + Read more ... If the customer:
|
4 |
Parenting Payment Partnered (PPP) due to Disability Support Pension (DSP) transition group with partial capacity to work + Read more ... Is the customer receiving PPP because they are in the DSP transition group and transferred to PPP and have a partial capacity to work?
|
5 |
Additional PES qualifications + Read more ... To qualify for PES, the customer must:
If a customer is waiting for approval of a PES or ABSTUDY PES qualifying pension or payment determine if the customer meets all other eligibility criteria first. Is the customer waiting for approval of a PES or ABSTUDY PES qualifying pension or payment?
|
6 |
Customer does not currently receive a qualifying payment + Read more ... Has the customer submitted a claim for a qualifying pension or payment?
|
7 |
Check all qualification for PES are met + Read more ... Customers with a Social Security Act qualifying payment only need to provide identity documentation if they did not meet Identity Confirmation requirements when claiming their qualifying payment. For DVA customers, identification documentation is required if their identity is not confirmed with Services Australia. Does the customer meet all the PES qualifications or, will they meet within 13 weeks of the date of lodgement?
|
8 |
ABSTUDY Incidentals only + Read more ... An earlier grant date may apply to ABSTUDY PES. To confirm the correct date of grant, the claim must be assessed by an ABSTUDY Processing Service Officer. Use Fast Note - select Auto text, Students, ABSTUDY & Apprentices > Enquiry > ABSTUDY PES suitability enquiry Change the claim status to:
Procedure ends here. |
9 |
What qualifying study is the student undertaking or intending to undertake + Read more ... To qualify for PES, the customer must be:
Other resources that may assist in assessing a PES claim include:
Is the student undertaking or intending to undertake qualifying study for PES?
|
10 |
Department of Veterans' Affairs (DVA) recipient and required clearance requests + Read more ... PES claims submitted online will have a priority keyword SUPDVA if they are a DVA recipient. These claims have a higher priority in WLM for allocation, to allow for the lead time to obtain DVA clearance. Check for Identity Confirmation. PES customers receiving a qualifying DVA payment will be required to provide confirmation of identity. In most cases, their identity has not been confirmed to Services Australia. Ensure appropriate identity has been requested in the new claim, if it has not issue a request using the Request for Information (RFI) workflow. The DVA Clearance Team can confirm if the customer is receiving a qualifying payment from DVA.
Ensure all relevant information is recorded. Change the claim Status to:
Normal processing rules around holding claims and duration of the hold apply. The DVA Clearance Team will update information on the DVA Payments screen (DVA/DVAS) to confirm eligibility. Once clearance is received check, if the customer is receiving a qualifying payment from DVA, |
11 |
Customer transferred onto a PES qualifying payment and claimed PES prior to transfer date + Read more ... PES claims may incorrectly reject Qualifying payment not current (CQP) where the:
If the customer meets all other PES qualifications:
Ensure the claim finalisation Note has details of workaround used, see Table 2. |
12 |
Claim not required to be assessed + Read more ... If the claim is not required to be assessed, manually change the status of the claim to Not Required. Examples of appropriate use include, but not limited to:
Note: changing the claim to Not Required is final and the status cannot be changed again. Before changing the status to Not Required, consider all other actions on the record to reduce the risk of changing the status incorrectly. In Process Direct:
Where a claim has had a Not Required status incorrectly applied, another claim will need to be manually created, using the SOA Shell application in Process Direct. Procedure ends here. |
Assessing and coding PES claims
Table 2
Step |
Action |
1 |
Process the new claim via Process Direct + Read more ... Check if the claim is a paper claim by opening the claim slider. For paper claims, use information from the scanned SY004 form (Documents screen) to process the claim in the relevant screens. Determine if an allowable time assessment is required see Assessing satisfactory progress and allowable time for tertiary students for Pensioner Education Supplement (PES): Is an allowable time end date coded?
|
2 |
Allowable time end date (ATED) coding within PES new claims + Read more ... When an ATED is coded for a PES new claim, the system:
To make sure customers get the correct advice the ATED must be coded based on if it is after, or before the date the claim is assessed. If the allowable time end date is:
|
3 |
Coding the PES claim + Read more ... Review the information in the PES claim to code the claim. Note: students undertaking a Startup Year Course to be eligible for a student payment, must:
For information on coding the Customer Study Details (EDCH) screen see Coding new study details:
If the customer is:
Note: in limited circumstances information automatically populated on the EPDC screen may not be correct. If a manual start date is to be coded, ensure the RSN manual start date field is coded as MWA - manual workaround. |
4 |
Coding the EPDC screen for Department of Veterans' Affairs (DVA) recipients + Read more ... Additional coding is required on the EPDC screen for customers in receipt of a qualifying DVA payment. Code the DVA Payment Type based on the DVA payment the customer is receiving. For:
|
Finalising PES claims
Table 3
Step |
Action |
1 |
Outcome of claim + Read more ... Grant claim, go to Step 4 Reject claim, because of one of the following reasons:
For all other rejection reasons including, allowable time end date being on or earlier than the date of processing, go to Step 3 |
2 |
Streamline rejection + Read more ... If the PES claim is to be streamline rejected, the claim does not need to be coded before completing the rejection. Note: make 1 genuine attempt to contact the customer by phone before finalising the decision. Streamline reject the claim:
|
3 |
Manual rejection + Read more ... Check cancellation, suspension and rejection reason codes. Only use rejection code 'Other' (OTH) if no other rejection code is appropriate. Note: make 1 genuine attempt to contact the customer by phone before finalising the decision. If rejecting the claim due to 'Allowable Time Reached' or 'Start Date is >13 weeks in the future' use rejection reason 'OTH'. A manual rejection letter must be issued after finalising the claim.
After the rejection activity is finalised go to the AL screen. Has a Manual Follow-up (MFU) activity been created?
|
4 |
Granting of a claim + Read more ... Select Assess. On the Entitlements (ELD) screen, check the outcome. Is the outcome correct?
|
5 |
Work around for X511AS error + Read more ... When this error occurs wait until after the first entitlement period of the new payment has passed before processing the claim as the bug no longer occurs after the end of the first entitlement period. For example, if granting from 14 April 2009, the first entitlement period is 14 April 2009 to 27 April 2009. On 28 April 2009 (or later), the bug will not occur and the claim can be finalised. Note: the customer will receive their first payment one day late if the claim is finalised on the first day after the end of the entitlement period. |
6 |
Finalisation Note + Read more ... The Claim Finalisation Note displays. Edit or add any extra details required. Select Finalise to complete the claim. A confirmation dialog box appears. Select OK. Where a checklist of scans displays, mark each as complete using the tick boxes to close them. Has an Education Entry Payment (EdEP) been granted during the PES claim process?
|
7 |
Record the outcome of the PES claim and further actions + Read more ... If the claim has not auto-generated a Note create a Note including relevant Guide and Act references and all additional information. See Online Document Recording (ODR). Has an Allowable Time End Date (ATED) been coded within the claim, or does an ATED need to be coded now the claim has been finalised?
|
8 |
Allowable time end date (ATED) follow up actions + Read more ... If a claim has been granted for a period and then cancelled due to Allowable Time Reached:
If an ATED needs to be coded on the Customer Study Details (EDCH) screen that is later than the date of processing:
Is the customer in receipt of Carer Payment?
|
9 |
Carer Payment (CP) + Read more ... Carer Payment customers hours of study may impact their ongoing entitlement to CP, see Carer Payment (CP) and Carer Allowance (CA) carer undertakes paid employment, self-employment, voluntary work, education or training activities. After the PES claim has been finalised for a CP customer create a Fast Note to notify Carer Payment trained Service Officers that a customer has started studying:
|
10 |
Check eligibility to Education Entry Payment + Read more ... The customer may be eligible to receive Education Entry Payment. Check if the customer meets eligibility requirements to receive EdEP, see Education Entry Payment (EdEP). Is the customer eligible to receive EdEP?
|
11 |
Quality Management Officers + Read more ... Complete QMA checks as per existing processes. Check if there is an existing Commenced Study - CPAS to be updated open Fast Note on the record for Carer Payment customers. Check if there is an existing PES Allowable Time End Date open Fast Note on the customer's record. If there is an open Fast Note more action is needed from the QMA. If there is no open Fast Note Quality Management Officers must create one, using the Auto Text function: